Melbourne City Councillor Cathy Oake who claimed last Tuesday that the St Kilda Road section between Princes Bridge and Linlithgow Avenue was one of the worst Bicycle accidents spots has been proved to be false and misleading.
Geo-Spatail data of bicycle accidents show that the section of St Kilda Road in which the City of Melbourne proposes to construct a Latrobe Street style 350m bike lane costing $330,000 is not a a major source of accidents. There is growing concern and opposition to the roll out and implementation of Melbourne's Bicycle plan. There are a number of shortfalls in the consultation process with major stakeholders not consulted in the formation of the policy including Motorcyclists and Emergency services. Cathy Oake was chairman of the City Council's Transport Portfolio.
On Tuesday the City of Melbourne rejected a proposal to defer the development of the St Kilda Road Bike Lane and to undertake a comprehensive review of the Latrobe Street and Princess Bridge Bike lane developments.
The City of Melbourne failed to give due and proper consideration to the cheaper alternative "Chevron line delineated" bike lane design that would have allowed for 3-4Km safer bike path to be installed along St Kilda Road. The proposed 350m bike lane will do nothing to improve public safety.
Showing posts with label Public Safety. Show all posts
Showing posts with label Public Safety. Show all posts
Saturday, August 10, 2013
Monday, July 29, 2013
St Kilda Rd Bicycle Lane: Open Letter to the Lord Mayor and Councillors - City of Melbourne
Lord Mayor and Councillors
City of Melbourne
I am writing to request that the City of
Melbourne defer the development and construction of the proposed bike
lane in St Kilda Road and that the development be referred for
consideration at the next City of Melbourne Future Melbourne Committee.
The current City Council has not considered or approved the project other than approve the Council's Budget and 4 year plan.
There are a number of major issues of concern in relation to the proposed design that should be reviewed.
LATROBE STREET BIKE LANE
The Latrobe Street bike lane has been a complete disaster with growing concern about public safety and suitability of this design. The Lord Mayor himself on public radio has indicated as such and that the City of Melbourne needs to review the development and make a number of changes to the design including the removal of on street parking.
It would be prudent that such a review is completed prior to the commencement of construction of a similar bicycle lane in St Kilda Road.
PUBLIC SAFETY
The section of St Kilda Road between Princess Bridge and Linlithgow Avenue is widely used by bus operators and members of the public visiting with family and friends the Arts precinct and the neighboring Gardens.
Many with children, elderly or disabled passengers. The proposed design and lane separation would constitute a major risk to public safety to commuters and pedestrians and needs to be reconsidered in light of the problems identified as a result of the construction of the Latrobe Street bike path experiences
The proposed development could be in breach of the Equal Opportunities Act in that it severely disadvantages disabled by denying them access to safe parking. Council needs to contact and have reviewed the proposed design by the Victorian Disabilities Advocate
The proposed lane design will force motorists to park on the outside of the bike lane three meters from the footpath creating a major risk to pedestrian and motorist safety.
Passengers
alighting from parked vehicles will have to negotiate a balancing act
on the one meter concrete strip and check for bicycles racing down the
bike lane whilst running to reach the footpath on the other side. The
design will place families with children and the elderly safety at
serious risk. Mums with prams or those with wheel chairs will not be
able to safely park their cars in the 3 hour parking zones. Bus drivers
and taxi operators will have similar safety concerns when dropping off
passengers.Drivers exiting a vehicle will be forced into opening car doors into congested on coming road traffic causing a further risk to motorist safety.
BUS PARKING - DROP OFF ZONE
The proposed design is a serious threat to the safety of passengers exiting the bus with passengers having step onto the one metre concrete separation barrier, then wait to ensure there are no bicycles bearing down on them before crossing the two metre bike path on to the adjacent footpath. The situation is made worst when there are 40 other passengers all wanting to exit the bus at the same time and even worst again in an emergency situation.
ALTERNATIVE DESIGNS
The City of Melbourne needs to reconsider alternative designs that addresses the above safety issues.
In discussion with Senior City of Melbourne Engineers I understand that there was a preferred alternative design similar to the design implemented in Claredon Street East Melbourne.
A better and much cheaper option is to widen the existing bike path and delineate it from parked cars by line marking as is the case in Clarendon Street East Melbourne. This would allow sufficient room for cyclists to pass without entering in to the parked car door zone and for the same cost could be extended past the Shine up to Domain Road and beyond. They could also apply the same treatment to the other side adjacent to the Art Gallery and Concert Hall giving ratepayers more value for their dollar.
The alternative design would be cheaper in cost to install and would allow the City of Melbourne to greater flexibility in implementing and changes that may be required.
The Claredon Street design solution addresses many of not all of the major concerns in relation to public safety without placing at risk commuter and pedestrian safety.
Further the Claredon St design solution is consistent with the other section of bicycle lane in St Kilda Road and Princes Bridge. The savings in cost would allow the city of Melbourne in conjunction with VicRoads to extend the alternative design bike path to include the entire stretch of St Kilda Road in both directions further adding to cyclist and pedestrian safety.
EMERGENCY ACCESS
St Kilda Road is a major access point for emergency vehicles from and to The Alfred Hospital in Commercial Rd
The construction of the separated bicycle lane barrier would limit movement and egress options for emergency vehicles.
As I understand Emergency services have not been
consulted on the proposed design and the alternative options. The
implementation of the Claredeon Street design solution would enable
greater flexibility and access for emergency vehicles.
.
.
REVIEW OF PROPOSED DEVELOPMENT
It is fundamental and prudent that the City of Melbourne that the Council undertake a comprehensive review of the Latrobe Street bike lane and the proposed design of the St Kilda Rd bicycle plan.
In light of the above issues of concern. Should any person be injured as a result of the proposed development Council would be held liable for any injury and the accident would not be covered by the Victorian Motor Accident Insurance Scheme if a vehicle is not involved.
I therefore request that the City of Melbourne as a
matter of urgency defer the construction of the proposed development and
refer the project for further consideration at a Future Melbourne
Committee and that members of the public and other stakeholders be
proposed the opportunity to make further submission on the impact of the
proposed design and the alternative options/
Should you require further information I can be contacted via return email
Yours faithfully
Anthony van der Craats
South Yarra
cc Victorian Minster for Roads, State Opposition Spokesperson for Roads, RACV, Members of Parliament and the Media
Labels:
Bicycle Lanes,
Engineering Services,
Lord Mayor,
Public Safety
Saturday, July 27, 2013
Proposed St Kilda Rd Bike Plan Threat to Public Safety
Melbourne Bus and taxi operators have expressed concern about the safety of its passengers if the Melbourne City Council's proposed St Kilda Road Bike Lane development is allowed to proceed.
The proposed design is a serious threat to the safety of passengers exiting the bus with passengers having step onto the 1 metre stone separation barrier, then wait to ensure there are no bicycles bearing down on them before crossing the 3 metre bike path on to the adjacent footpath. The situation is worst when there are 40 other passengers all wanting to exit the bus at the same time and would even worst again in an emergency situation.
Bus and taxi drivers are joining the chorus of other community groups opposed to the proposed $330,000 bike plan design which is scheduled to be installed next month.
Residents, business and community groups are calling on the City Council to scrap the plan and hold am open public review of the proposal.
Community advocate and former City Councillor David Nolte has said that Cr Richard Foster has expressed concern at the proposal and t bis understood he has asked that the matter be brought before Council.
Other Councillors have also expressed concern but said that the issue was in the hands of the Lord Mayor Robert Doyle who was opposed to any review in spite growing concern over its impact on public safety.
Cr Stephen Mayne, who claims to be an advocate for open and transparent government, was not prepared to discuss this issue.
UPDATE: Cr Foster as indicated that he will be calling for a halt to the project and that a report be presented in detail at the next Future Melbourne Committee
The proposed design is a serious threat to the safety of passengers exiting the bus with passengers having step onto the 1 metre stone separation barrier, then wait to ensure there are no bicycles bearing down on them before crossing the 3 metre bike path on to the adjacent footpath. The situation is worst when there are 40 other passengers all wanting to exit the bus at the same time and would even worst again in an emergency situation.
Bus and taxi drivers are joining the chorus of other community groups opposed to the proposed $330,000 bike plan design which is scheduled to be installed next month.
Residents, business and community groups are calling on the City Council to scrap the plan and hold am open public review of the proposal.
Community advocate and former City Councillor David Nolte has said that Cr Richard Foster has expressed concern at the proposal and t bis understood he has asked that the matter be brought before Council.
Other Councillors have also expressed concern but said that the issue was in the hands of the Lord Mayor Robert Doyle who was opposed to any review in spite growing concern over its impact on public safety.
Cr Stephen Mayne, who claims to be an advocate for open and transparent government, was not prepared to discuss this issue.
UPDATE: Cr Foster as indicated that he will be calling for a halt to the project and that a report be presented in detail at the next Future Melbourne Committee
Labels:
Bicycle Lanes,
Public Safety,
Richard Foster,
Stephen Mayne
Wednesday, May 08, 2013
City of Melbourne denies any responsibility for permits to construct a hoarding
In a surprised turn around the City of Melbourne has come out and denied that it has any responsibility to issue permits for hoardings on private property.
Previously the City of Melbourne had stated:
The City of Melbourne has a permit application for hoardings which comes with a fee for service. They have published a full list of permits required and a hoarding, fence and advertising sign is on the list which is also included in the
City of Melbourne Local Law 2009.
Part 7 BUILDING STANDARDS Compliance with Code
Part 13 PERMITS When is a permit required under this Local Law?
What the response from the City of Melbourne (published below) failed to mention or make clear was that under the local law a hoarding (Both on public land and on private land) must comply with the City of Melbourne Construction Management Plan and the relevant design standards related to height and wind loading The code of practice, (1.4) which is referenced in the City of Melbourne Local Law, stipulates a maximum height of 2.4m and ability to withstand wind loads to AS1170.2 standards
Under the the Code of Practice
With all the word games and "intricate interconnect overlap and complexities" that surround this issue there is a clear need for the City of Melbourne to undertake an independent review of the legislative provisions governing public safety on building sites and the City Council.
This should be done as a matter of urgency and without delay or waiting pending the outcome of the Coroner's report or other investigations that are currently underway in relation to the March 28 Swanston Street Wall Collapse. It will have to be done eventually,. The sooner they start the better
Council response dated: Tuesday, 7 May 2013 12:08
I refer to the Future Melbourne Committee Meeting of 15 April 2013 – Question without Notice in relation to 555-591 Swanston Street and 2-76 Bouverie Street, Carlton and provide the following response.
Question:
“Did the City of Melbourne issue a permit for the construction of the new hoarding on the CUB Swanston Square project site? The height being significantly taller than the 2.4m maximum permitted height pursuant to the City of Melbourne Construction Management Plan Guidelines.
Has the City of Melbourne inspected the site since the new hoarding was constructed? If not, why not?”
No permit has been issued for the construction of a hoarding.
The temporary fence/hoarding is located on private property. In this instance a permit is not required under the Activities Local Law 2009.
The structure is also exempt from a building permit under the Building Regulations 2006
(Sch. 8).
The structure satisfies Element 1, Item 1.5 of the City of Melbourne Construction Management Plan Guidelines as:
1. It is a solid barrier
2. The barrier prevents viewing; and
3. The barrier should restrict unauthorised entry
It is the owner’s responsibility to ensure the structure is designed, installed and maintained in accordance with engineering principles and must satisfy any relevant standards.
City of Melbourne officers attended the site shortly after the barrier was erected.
T: 03 9658 8400 | M: 0429 502 043 | F: 03 9658 9891
|www.melbourne.vic.gov.au | |www.melbourne.vic.gov.au/whatson
Previously the City of Melbourne had stated:
We can confirm that the City of Melbourne has not issued a permit for the structure attached to the wall.Developers, builders and owners along with lawyers will have a field day with this one. Anarchy reigns in Melbourne's Streets I wonder what the Coroner and the Work Safety inquiries will make of this one.
There are four relevant legislative frameworks – Planning, Building, Occupational Health and Safety and Local Laws. There are intricacies in the way in which these interconnect and overlap. These complexities are likely to be considered by the investigating authorities.
A CMP (Construction Management Plan) does not replace the need for Planning, Building or Local Laws approval for specific works. These must be sought separately.
The City of Melbourne has a permit application for hoardings which comes with a fee for service. They have published a full list of permits required and a hoarding, fence and advertising sign is on the list which is also included in the
City of Melbourne Local Law 2009.
Part 7 BUILDING STANDARDS Compliance with Code
Part 13 PERMITS When is a permit required under this Local Law?
What the response from the City of Melbourne (published below) failed to mention or make clear was that under the local law a hoarding (Both on public land and on private land) must comply with the City of Melbourne Construction Management Plan and the relevant design standards related to height and wind loading The code of practice, (1.4) which is referenced in the City of Melbourne Local Law, stipulates a maximum height of 2.4m and ability to withstand wind loads to AS1170.2 standards
Under the the Code of Practice
Item 2. Definitions ... "Hoarding" means "a high temporary fence or structure enclosing a demolition site or a building site during building works, to restrict access and provide side protection to the public"
Item 4. Hoardings
4.1 ... Hoarding screens must be constructed of closely boarded timber or plywood between 1.8m to 2.4m in height to secure a building site and form a barrier against noise, dust and debris.
... Hoardings are to be designed to withstand wind loads to AS 1170.2 with counterweights as necessary to prevent overturning. In addition hoardings adjoining excavations are to be designed to withstand a lateral line load of 0.75 kN/m applied at a height of 1 metre from the base and suitably guarded by barriers to prevent vehicular impact.
With all the word games and "intricate interconnect overlap and complexities" that surround this issue there is a clear need for the City of Melbourne to undertake an independent review of the legislative provisions governing public safety on building sites and the City Council.
This should be done as a matter of urgency and without delay or waiting pending the outcome of the Coroner's report or other investigations that are currently underway in relation to the March 28 Swanston Street Wall Collapse. It will have to be done eventually,. The sooner they start the better
Council response dated: Tuesday, 7 May 2013 12:08
I refer to the Future Melbourne Committee Meeting of 15 April 2013 – Question without Notice in relation to 555-591 Swanston Street and 2-76 Bouverie Street, Carlton and provide the following response.
Question:
“Did the City of Melbourne issue a permit for the construction of the new hoarding on the CUB Swanston Square project site? The height being significantly taller than the 2.4m maximum permitted height pursuant to the City of Melbourne Construction Management Plan Guidelines.
Has the City of Melbourne inspected the site since the new hoarding was constructed? If not, why not?”
Response:
No permit has been issued for the construction of a hoarding.
The temporary fence/hoarding is located on private property. In this instance a permit is not required under the Activities Local Law 2009.
The structure is also exempt from a building permit under the Building Regulations 2006
(Sch. 8).
The structure satisfies Element 1, Item 1.5 of the City of Melbourne Construction Management Plan Guidelines as:
1. It is a solid barrier
2. The barrier prevents viewing; and
3. The barrier should restrict unauthorised entry
It is the owner’s responsibility to ensure the structure is designed, installed and maintained in accordance with engineering principles and must satisfy any relevant standards.
City of Melbourne officers attended the site shortly after the barrier was erected.
Angela
Meinke | Manager Planning and Building | City Planning and
Infrastructure
City of Melbourne | Council House 2, 240 Little Collins Street Melbourne 3000 |
GPO Box 1603 Melbourne 3001T: 03 9658 8400 | M: 0429 502 043 | F: 03 9658 9891
|www.melbourne.vic.gov.au | |www.melbourne.vic.gov.au/whatson
Labels:
Engineering Services,
Legal,
Public Safety,
The Wall
Monday, May 06, 2013
ABC Error in Reporting on Council's Press Release on Wall Collapse
The ABC, following a complaint in relation to an article on the Wall
collapse in Swanston Street, reported that the City of Melbourne was not
required to issue a permit for the hoarding. The ABC reporter was wrong.
ABC's response to the complaint
ABC's response to the complaint
ABC News acknowledges the reporter misinterpreted the press release issued by the City of Melbourne and consequently inadvertently misrepresented the council’s position.
News advise that the release came after several days of phone calls by the reporter to the City of Melbourne asking about whether or not a council permit was required and, if so, whether one was issued. She was told by council officers that the situation regarding permits was confused as there were a number of different authorities involved. The confusion was compounded by the press release, which was not received until late in the day. On reading the release she came to the conclusion that it was indicating that the council did not need to issue a permit.
ABC News apologises for the error. The story has been corrected and an editor’s note attached.
The City of Melbourne Press release did not state that the Council "did not need to issue a
permit" to the contrary it stated that
We can confirm that the City of Melbourne has not issued a permit for the structure attached to the wall.
There are four relevant legislative frameworks – Planning, Building, Occupational Health and Safety and Local Laws. There are intricacies in the way in which these interconnect and overlap. These complexities are likely to be considered by the investigating authorities.
A CMP (Construction Management Plan) does not replace the need for Planning, Building or Local Laws approval for specific works. These must be sought separately.The City of Melbourne's responsibility of the subject of a number of inquiries including the Coroner, Work Safety and the Building Commission. The Council has refused to undertake an independent inquiry into its responsibility on the administration of public safety, it's Local laws and liability
Tuesday, April 30, 2013
March for Public Safety: Melbourne Community in Solidarity with Workers
The Union rally follows on from four deaths associated with GroCon buildings sites in Melbourne. One Worker who fell from a construction site crane and three innocent pedestrians who were killed when a hoarding and brick wall collapsed on March 28.
The City of Melbourne needs to undertake an internal review of its role in the tragic events and its statutory obligations.
- Is GroCon being given favourable consideration and are they exempt from local laws and prosecution?
- Has the City of Melbourne been negligent or are they turning a blind eye in a gentleman's agreement?
There is a need for a fourth Statutory compliance and review which must look closely at the role of the City of Melbourne in overseeing Construction site public safety.
The Union movement plans further rallies should the government inquires seek to scape goat or fail to hold to account those responsible. This includes the City of Melbourne and the State Government
Labels:
Engineering Services,
Governance,
Legislation,
Public Safety,
The Wall
Monday, April 29, 2013
CFMEU: Tuesday March for Safety
The CFMEU (Construction Forestry Mining Employees Union) and Victoria's Trade Unions will be marching next Tuesday April 30 in support of Safety on Melbourne's Building sites. The march begins at Trades Hall in Victoria Street, and will proceed to the Swanston Street site of last month's tragedy for a minute's silence as a sign of respect.outside the GroCon CUB building site on Swanston Street.
The City of Melbourne still has not provided information why it had not issued a permit or inspected the building site hoarding which collapsed on March 28.killing three innocent pedestrians.
The City of Melbourne continues to shift blame and avoid accountability for for its own failings. Public Safety is the prime directive and obligation of the City Council. Stephen Mayne describing public concerns about safety on the GroCon site as "Grandstanding"
Tuesday, April 23, 2013
Negligence or Corruption a question on Twitters mind
Questions remain unanswered following last months fatal wall collapse with the City of Melbourne ducking for cover and in lock down mode avoiding responsibility.
According to a City of Melbourne spokesperson a permit is required for the construction of a hoarding on a building site. The City of Melbourne in its statement published on April 9 stated that a permit was not issued for a hoarding on the GroCon Swanston Street building site that collapsed on March 28 killing three pedestrians.
When asked on April 16 if the Council had issued a permit for the NEW hoarding on thee GroCon Swanston Street site and if the Council Officers had inspected the site and if not why not? Councillor Stephen Mayne, Chairman of the Council's Governance portfolio was unable to answer and took the question on notice.
A week has passed and still the City of Melbourne has not been able to respond to this important and yet simple question.
Questions are being asked if the Council is guilty of contributory negligence for the death of three innocent people by failing to fulfill its statutory obligations and/or if Council staff had received inducements to turn a blind eye to the requirement to issue a permit for the construction of a hoarding? Both the new and old hoardings were taller then the maximum height of 2.4m listed in the Council's Construction Management Plan guidelines.
It is a simple question and deserves an answer.
Council itself, and Councillor Mayne in particular, are now being compromised by the Council's failing to reply. Avoiding the question will not make it go away and only serves to undermine public confidence in the City Council's Administration.
The Lord Mayor, Robert Doyle, may also be tainted by the Council's lack of response with allegations being made that Councillor Doyle is actively seeking to block twitter discussion and review of his administration.
According to a City of Melbourne spokesperson a permit is required for the construction of a hoarding on a building site. The City of Melbourne in its statement published on April 9 stated that a permit was not issued for a hoarding on the GroCon Swanston Street building site that collapsed on March 28 killing three pedestrians.
When asked on April 16 if the Council had issued a permit for the NEW hoarding on thee GroCon Swanston Street site and if the Council Officers had inspected the site and if not why not? Councillor Stephen Mayne, Chairman of the Council's Governance portfolio was unable to answer and took the question on notice.
A week has passed and still the City of Melbourne has not been able to respond to this important and yet simple question.
Questions are being asked if the Council is guilty of contributory negligence for the death of three innocent people by failing to fulfill its statutory obligations and/or if Council staff had received inducements to turn a blind eye to the requirement to issue a permit for the construction of a hoarding? Both the new and old hoardings were taller then the maximum height of 2.4m listed in the Council's Construction Management Plan guidelines.
It is a simple question and deserves an answer.
Council itself, and Councillor Mayne in particular, are now being compromised by the Council's failing to reply. Avoiding the question will not make it go away and only serves to undermine public confidence in the City Council's Administration.
The Lord Mayor, Robert Doyle, may also be tainted by the Council's lack of response with allegations being made that Councillor Doyle is actively seeking to block twitter discussion and review of his administration.
Labels:
GroCon,
Public Safety,
Robert Doyle,
Stephen Mayne,
The Wall
Wednesday, April 17, 2013
Council's Road Safety Plan placed on hold pending review
Melbourne City Council yesterday deferred, at the request of representatives of Melbourne's Motorcycle and Scooter Riders' Associations. The adoption of the City of Melbourne Road Safety Plan amidst concern that the report and the consultation process was flawed and lacking public confidence.
Spokesperson for the Motorbike and Scooter riders said "The Council report included a number of mother hood statements and lacked causing on the needs of pedestrians and bicyclists but ignore concerns of two wheel power riders and other road users"
Community activist and scooter rider, Anthony van der Craats, said that "The City Council was "Engineering Congestion" and that the city was making road safety worst as a result. There is a need to stop and review the impact of the Council's Transport Strategy plan so that all road users were given equal consideration".
The Lord Mayor, Robert Doyle, also expressed concern that report did not include in a holistic manner consideration of other road users such as cars, trucks and vans, all which need to consulted.
Emergency Access Restricted
Mr van der Craats said "The Road Safety Report also failed to consult Emergency Services such as the Metropolitan Fire Brigade and Ambulance Victoria".
During question time Mr van der Craats expressed his condolence for Melbourne's Sister City Boston and the Terrorist attacks that were carried out earlier in the day.
These tragic events raised concern as to Melbourne's preparedness for such emergencies. There is growing concern recent road works and engineering restrictions in the City may have an adverse impact on the response time of Emergency Vehicles in the City.
Mr van der craats called on the City of Melbourne as part of is Road Safety Strategy to undertake a serious of Stress Testing involving the emergency services to ensure that the city engineering services do not prevent or hinder emergency service response times. "There is ongoing concern that an event such as what occurred in Boston today could be a disaster if Firetrucks and Ambulances were not able to pass trams blocking the major transit routes. The new Super Stops and bicycle paths in particular constitute a real risk to public safety"
Councillor Richard Foster earlier today reported that he will not be supporting the reduction of traffic lanes on Princess Bridge from two lanes to one.
Princess Bridge is a major access route to the City and the nearby Alfred Emergency Critical Care Hospital. A reduction in vehicular access could have serious impact on Ambulance response times and could conceivable cost lives.
The fact that the City of Melbourne had not consulted our emergency services or reviewed their needs was a major oversight.
The City Engineers proposal to create further congestion on Princes Bridge has been rejected by the RACV, VicRoads and other community groups.
Victoria' Premier, Dr Napthine, on Radio 3AW Neil Mitchel earlier this week, cast doubt over the proposal following overwhelming community rejection.
Mr van der Craats said "There is no support other than from Council Engineers and the Green Bicycle Lobby group. The State Government must rain in the City Council and put an end to the Congestion creation strategy pursued by the Greens".
Community representatives will meet with Opposition Spokesperson Luke Donellan to seek his support in stopping this ill-considered proposal
The Engineering Services Director, Geoff Robinson, has until July 9 to address stakeholder concerns and present a workable and accepted Road Traffic proposal
Tuesday, April 16, 2013
Fostering a Bridge to Reason
A MELBOURNE councillor has voiced
concerns about a controversial plan to make Princes Bridge more
bike-friendly by removing two car lanes, saying other options should be
explored first.
Cr Richard Foster said a better delineation of the bike lanes over the busy bridge should be among them. "We haven't yet made efforts to colour, pave or widen them . . . We have a line painted on a ground with a symbol of a bike, and I think we can do a lot better than that," Cr Foster said.
"These are the sorts of things that could well relieve congestion without first interfering with traffic lanes."
The Herald Sun revealed the Melbourne City Council proposal, which would cost about $150,000, last month.
Cr Foster said there were also "significant pedestrian access issues" with the nearby tram stop
Cr Richard Foster said a better delineation of the bike lanes over the busy bridge should be among them. "We haven't yet made efforts to colour, pave or widen them . . . We have a line painted on a ground with a symbol of a bike, and I think we can do a lot better than that," Cr Foster said.
"These are the sorts of things that could well relieve congestion without first interfering with traffic lanes."
The Herald Sun revealed the Melbourne City Council proposal, which would cost about $150,000, last month.
Cr Foster said there were also "significant pedestrian access issues" with the nearby tram stop
Sunday, April 14, 2013
VICTORIAN MOTORCYCLE & SCOOTER RIDERS OPPOSE THE MELBOURNE ROAD SAFETY PLAN
MEDIA RELEASE
VICTORIAN MOTORCYCLE & SCOOTER RIDERS
OPPOSE THE MELBOURNE ROAD SAFETY PLAN
Powered Two
Wheeler (PTW) rider advocacy groups including the Victorian Motorcycle Council
(VMC), the Independent Riders Group (IRG) and the Victorian Scooter
Riders Association (VSRA) have collectively called for postponement of the
vote endorsing the Melbourne Road Safety Plan. Their concerns are the Plan fails to enhance the
safety of PTW riders and fails to meet its goal to:
“Create a safe, comfortable and richly engaging urban environment where pedestrians, cyclists and motorcyclists are welcomed and supported through world leading road safety practices” and “to “recognise the needs
“Create a safe, comfortable and richly engaging urban environment where pedestrians, cyclists and motorcyclists are welcomed and supported through world leading road safety practices” and “to “recognise the needs
of pedestrians, cyclists and
motorcyclists in street design”
Stephen Bardsley, VSRA spokesperson said, "Despite raising concerns back in October 2012, the Plan fails to recognise the needs of PTW riders in any meaningful way. It's a disgrace."
Damien Codognotto from the IRG said, “Whereas it’s good PTW’s were mentioned in the Plan, that’s all we got and it simply doesn't give riders a fair go."
Peter Baulch from the VMC said, "The Plan proposes no initiatives that encourage the most efficient and fastest growing form of road transport to enter the city, it also fails to recognise their needs."
The spokespersons for all
three organisations are collectively disappointed that whereas local
Governments all over the World are implementing policies to encourage
Motorcycle and Scooter Riders into CBD’s, the City of Melbourne appears to have
failed its obligations in this regard. This when:
► Evidence shows the answer to the World's urban
traffic congestion may be as simple as creating
policies promoting the use of PTW’s, the fastest growing mode of transport in Melbourne.
policies promoting the use of PTW’s, the fastest growing mode of transport in Melbourne.
► Research released in 2012 proved if just 10% of all private cars were to be replaced
with
PTW’s then traffic congestion would be reduced by up to 40%, to the benefit of all road users.
PTW’s then traffic congestion would be reduced by up to 40%, to the benefit of all road users.
The VMC, IRG and VSRA are
united in calling for the Melbourne City Council to postpone endorsing the plan
and to initiate genuine stakeholder review.
End of Media Release
VMC
Spokesperson – Robert Salvatore
Telephone: 0409 416 230
email: Rob.Salvatore@qenos.com
Spokesperson – Robert Salvatore
Telephone: 0409 416 230
email: Rob.Salvatore@qenos.com
IRG
Spokesperson – Damien Codognotto
Telephone: (03) 9846 8621
email: d.codognotto.oam@bigpond.com
Spokesperson – Damien Codognotto
Telephone: (03) 9846 8621
email: d.codognotto.oam@bigpond.com
VSRA
Spokesperson - Stephen Bardsley
Telephone: 0409 848 428
email: okeh1@bigpond.com
Spokesperson - Stephen Bardsley
Telephone: 0409 848 428
email: okeh1@bigpond.com
Labels:
Engineering Services,
Motorcycles,
Public Safety,
Road Safety,
Scooters